20241010 - from owner - mural work
|
20250922 - to owner - pricing set
|
2025-09-22 10:23:35 -05:00 |
|
20250717 - from LL - existing documentation
|
backgrounds
|
2025-11-13 12:01:40 -06:00 |
|
20251009 - lighting consultant - emergency lighting
|
backgrounds
|
2025-11-13 12:01:40 -06:00 |
|
20251202 - from Kitchen Supplier - spec book & plans
|
20251211 - Revisions-1
|
2025-12-11 20:41:12 -06:00 |
|
20251203 - to Owner and Kitchen Supplier - marked up plans
|
20251211 - Revisions-1
|
2025-12-11 20:41:12 -06:00 |
|
20251204 - from GC - MEP drawings
|
20251211 - Revisions-1
|
2025-12-11 20:41:12 -06:00 |
|
20251205 - concrete sealing submittal - 20251209
|
20251211 - Revisions-1
|
2025-12-11 20:41:12 -06:00 |
|
20251205 - from GC - concrete mix submittal - 20251208
|
20251211 - Revisions-1
|
2025-12-11 20:41:12 -06:00 |
|
20251205 - glass and glazing submittal - 20251215
|
20251218 - to GC and Owner - Revision 2
|
2025-12-18 19:59:03 -06:00 |
|
20251205 - toilet accessories and fire extinguishers - 20251215
|
20251218 - to GC and Owner - Revision 2
|
2025-12-18 19:59:03 -06:00 |
|
20251208 - from GC - door and hardware submittal - 20251208
|
20251211 - Revisions-1
|
2025-12-11 20:41:12 -06:00 |
|
20251208 - to GC - reviewed MEP drawings
|
20251211 - Revisions-1
|
2025-12-11 20:41:12 -06:00 |
|
20251209 - from GC - ceiling submittal - 20251210
|
20251211 - Revisions-1
|
2025-12-11 20:41:12 -06:00 |
|
20251210 - from plumbing sub - mop sink
|
20251211 - Revisions-1
|
2025-12-11 20:41:12 -06:00 |
|
20251211 - from GC - paint colors - 20251217
|
20251218 - to GC and Owner - Revision 2
|
2025-12-18 19:59:03 -06:00 |
|
20251211 - from GC - plumbing fixture submittal - 20251217
|
20251218 - to GC and Owner - Revision 2
|
2025-12-18 19:59:03 -06:00 |
|
20251215 - from Kitchen Supplier - walk-in cooler
|
20251218 - to GC and Owner - Revision 2
|
2025-12-18 19:59:03 -06:00 |
|
20251215 - permit approvals
|
20251218 - to GC and Owner - Revision 2
|
2025-12-18 19:59:03 -06:00 |
|
20251224 - from elect sub - transformer spec
|
Site Reports and Photos/20260310 - before substantial compelition
|
2026-03-11 13:17:23 -05:00 |
|
20251224 - from GC - Queue rail - 20251231
|
Site Reports and Photos/20260310 - before substantial compelition
|
2026-03-11 13:17:23 -05:00 |
|
20251230 - from GC - casework submittal - 20251231
|
Site Reports and Photos/20260310 - before substantial compelition
|
2026-03-11 13:17:23 -05:00 |
|
20260102 - from Kitchen supplier - refrig 64
|
Site Reports and Photos/20260310 - before substantial compelition
|
2026-03-11 13:17:23 -05:00 |
|
20260109 - from tile supplier - tile layout
|
Site Reports and Photos/20260310 - before substantial compelition
|
2026-03-11 13:17:23 -05:00 |
|
20260116 - from GC - tile layout
|
Site Reports and Photos/20260310 - before substantial compelition
|
2026-03-11 13:17:23 -05:00 |
|
20260209 - to GC and millworker - location of under counter refrig
|
Site Reports and Photos/20260310 - before substantial compelition
|
2026-03-11 13:17:23 -05:00 |
|
.gitkeep
|
Site Reports and Photos/20260310 - before substantial compelition
|
2026-03-11 13:17:23 -05:00 |